Marathon Ashland Petroleum

APTIM performed a turnaround (TAR) on Marathon Ashland’s 120,000 BPSD FCCU in Garyville, Louisiana. APTIM was responsible for the following design and detailed engineering:

  • Jigstands for the erection and assembly of the new reactor head and cyclones and for the support of the existing reactor head and cyclones.
  • Lift plans for removal and installation of the overhead line, reactor head and cyclones, reactor bottom head and stripper, J-bend and expansion joints and slide valves.
  • Temporary bracing plan to beef up the existing structure. Three floors were removed in order to replace the J-bend and expansion joints and slide valves. Pre-TAR work began on September 16, 2002 and the TAR mechanical work began on January 17, 2003. The TAR work was completed on February 18, 2003 and the post-TAR work was completed on April 25, 2003.

Contracting Entity: Marathon Ashland

APTIM. In Pursuit of Better.

Related Projects

Connect with APTIM

Learn more about our comprehensive turnaround and outage management capabilities.

    Subscribe to the APTIM Xchange Newsletter

    APTIM's newsletter, The APTIM Xchange, provides industry news flashes, regulatory updates, service spotlights, and topical columns from our subject matter experts.