Power Is the New Critical Path for Data Center Development

Power availability is shaping where data centers are built, how projects are phased, and when facilities can become operational. Evaluating utility capacity, infrastructure requirements, and delivery timelines early can help developers identify schedule risks before they delay development or power delivery.

This Week's Contributor

Walter Leclerc
Walter Leclerc Director, Data Center Practice APTIM | Environmental & Energy Solutions Email

The development schedule for a data center no longer depends only on how quickly the facility itself can be designed and built. For larger, more power-intensive projects, utility capacity and delivery timing can shape site selection, phasing, and the date a facility can begin operating.

A data center project can have land secured, approvals obtained, equipment in place, and design and construction substantially complete and still be unable to operate if the required power is not available when it is needed. Power availability and delivery timing therefore need to be evaluated alongside the traditional factors that determine the development schedule.

In many cases, the constraint lies beyond the property boundary, where utility capacity, transmission and distribution infrastructure, substations, permitting, and stakeholder requirements can shape the path to energization, or when power can be delivered to the facility. For data center development, power has become part of the critical path.

How Power Availability Is Reshaping Data Center Site Selection

Historically, site selection focused on factors such as land, fiber connectivity, tax considerations, labor, and proximity to customers. Those factors remain important. However, for large-scale and high-density data center development, power availability must now be evaluated alongside them.

For example, a site may look attractive from a real estate or connectivity perspective but be significantly less viable once the realities of electrical infrastructure are understood. Before a site decision is made, developers need to understand the available capacity, infrastructure requirements, delivery timeline, and dependencies that could affect energization. These questions can change site viability, phasing, infrastructure scope, and the project schedule.

Why Power Availability and Power-Delivery Timing Are Different

One of the most important distinctions in power planning is the difference between power availability and power-delivery timing. A utility may ultimately have the ability to serve a large load, but the infrastructure required to deliver that capacity may take years to plan, permit, construct, and commission.

For developers operating on aggressive schedules, this distinction is critical. The question is no longer, “Can this site get power?” It is, “Can this site get the required power when the project needs it?” That difference can fundamentally change the economics and schedule of a project.

Santa Clara, California, currently provides a clear illustration of what happens when power delivery becomes a constraint. Two large data centers in the Santa Clara market have faced delays in obtaining the full utility capacity required for operation. While the data centers have been developed, additional utility infrastructure and capacity are still being brought online to support their planned loads.

The constraint is not the construction of the facilities themselves; it is the infrastructure required to deliver the necessary power. Silicon Valley Power has been undertaking a major system expansion program valued at approximately $459 million and designed to increase system capacity and support long-term growth. The utility has indicated that the program is expected to be completed in 2028.

The example reinforces an important distinction for data center developers: A completed data center is not necessarily an operational data center. Capital can be invested in land, design, permitting, construction, and equipment while the ultimate energization date remains dependent on infrastructure that sits beyond the data center boundary and outside the project team’s direct control.

Integrating Power Planning into Data Center Development

Traditional project planning can break down when power is treated as a utility workstream operating alongside site development rather than as a core development constraint. When that happens, critical dependencies can remain hidden until they begin affecting the schedule.

When power is considered early, it can influence decisions throughout the development lifecycle. Actual utility capacity and delivery timelines can inform site selection. Campus design can account for electrical infrastructure requirements. Permitting strategies can incorporate off-site infrastructure, while construction sequencing can reflect energization milestones. Development schedules can then be built around realistic power-delivery assumptions rather than assumed availability dates.

Power planning therefore needs to be coordinated with engineering, environmental review, permitting, infrastructure, construction, and program management so utility milestones inform the broader development schedule.

Designing the Development Strategy Around Power Constraints

A single development may involve the owner, utility, engineers, environmental teams, regulators, contractors, local governments, landowners, and community stakeholders. Each has different responsibilities, schedules, priorities, and decision-making processes. The project schedule ultimately has to connect all of them.

That is why power cannot be viewed solely as an engineering issue. The technical solution may be straightforward, but implementing that solution can involve regulatory approvals, environmental reviews, land-use considerations, infrastructure, and stakeholder engagement. The earlier those dependencies are understood, the more options a project team has.

The fastest path is not always to build faster. Sometimes it is designing the development strategy around the constraints. That may mean evaluating power availability during site selection rather than after it, integrating utility milestones into the master development schedule, or identifying off-site infrastructure requirements early. The objective is not to eliminate uncertainty but to surface issues early enough to manage them.

How Off-Site Infrastructure Expands the Development Challenge

Power and other major infrastructure requirements, including water, can also create dependencies beyond the project boundary. As the scale of data center development grows, the infrastructure required to support projects becomes more visible to the communities around them. Transmission lines, substations, generation facilities, water infrastructure, land requirements, noise, and construction activity can all extend the project’s footprint well beyond the data center property boundary. Infrastructure planning is therefore intersecting with community and stakeholder engagement.

A technically feasible development strategy may still encounter challenges if community, regulatory, land-use, or local-government considerations are not understood early. The constraint is not always whether the infrastructure can be built. It can also be where the infrastructure can be permitted and delivered, and how stakeholder requirements affect that path.

Community and stakeholder engagement is becoming a more important part of that equation, not as a communications exercise but as a factor that can influence permitting, infrastructure development, project timing, and whether a project can move forward as planned.

How APTIM Supports Data Center Power & Development Planning

APTIM’s Data Center Solutions team coordinates permitting, environmental, infrastructure, engineering, and program management activities so power-related requirements can be evaluated alongside site selection, design, construction sequencing, and the development schedule. This coordination helps project teams understand what must happen, who must be involved, and when key milestones need to occur.

The goal is to connect technical power requirements with the regulatory, infrastructure, and program decisions that shape the development schedule.

Connect with APTIM’s data center solutions team to assess power-related development risks and coordinate permitting, infrastructure, and program management activities across your project portfolio.

CONNECT WITH APTIM’S DATA CENTER SOLUTIONS TEAM

Published November 2026